Barapukuria power plant
Barapukuria power plant shut for days
The Barapukuria 525MW coal-fired power plant in Dinajpur has completely shut down following a mechanical issue in its only running unit on Tuesday afternoon.
19 February 2025, 18:00 PM
Production fully suspended at Barapukuria power plant due to technical glitch
The shutdown has led to further power outages as the plant has the capacity to produce 275-megawatt of electricity.
10 September 2024, 06:04 AM
Not improving anytime soon
Nobody knows exactly when the power cuts will end
5 June 2023, 01:00 AM
Barapukuria plant: Shortage of coal may halt power generation
The Barapukuria 525MW coal-fired power plant may be mothballed once its current stock of coal is depleted later this month due to uncertainty over the resumption of coal supply from the nearby mine for underground development works.
6 July 2022, 18:00 PM
Barapukuria power plant shut down again after 9 days
One of the power generation units of the Barapukuria 525MW Coal Fired Power Plant in Parbatipur upazila of Dinajpur is shut down, after operating for nine days.
28 August 2018, 12:15 PM
Eid holidays: Barapukuria power plant unit goes into 5-day operation
A unit of Barapukuria coal-fired power plant, shutdown for over a month due to fuel crisis, will go into operation for five days from tomorrow to meet the demands of power during this Eid-ul-Azha, the plant officials say.
19 August 2018, 06:54 AM
Barapukuria Power Plant: Govt may go for coal import
The government is considering importing coal to run Barapukuria coal-based power plant in Dinajpur as supply from the country's lone coal mine, Barapukuria Coal Mining Company Ltd (BCMCL), has stopped.
28 July 2018, 18:00 PM
Find out the coal culprits
Prime Minister Sheikh Hasina has ordered forming a fresh committee to further investigate the disappearance of some 1.45 lakh tonnes of coal from Barapukuria coalmine and identify those responsible for it.
25 July 2018, 18:00 PM
ACC bars Barapukuria coalmine MD, 3 others from leaving country
Managing Director of Barapukuria Coal Mining Company Ltd (BCMCL) Habib Uddin Ahmed and three other high-ups of the company are barred from leaving the country, according to a letter sent by the Anti-Corruption Commission (ACC) to the emigration police.
24 July 2018, 14:57 PM
ACC forms body to probe Barapukuria coal crisis
The Anti-Corruption Commission (ACC) forms a committee to investigate the allegations of corruption at Barapukuria coalmine in Dinajpur that led to a crisis of coal at the Barapukuria Power Plant, prompting it to shut down indefinitely.
23 July 2018, 11:46 AM