Corruption in Matarbari Power Plant's Tool Imports

If this is not corruption, what is?

Take action against those overpricing products in Matarbari project
2 April 2024, 09:30 AM

Matarbari Power Plant: Tk 93 lakh for two pipe cutters!

On January 9, 2024, a small shipment weighing 344.5 kilograms arrived at Chattogram port. The shipment worth $250,863 (Tk 2.75 crore) contained 19 pieces of small tools such as hammer, metal pipe cutter and silicon guns imported for state-owned Coal Power Generation Company Bangladesh Limited (CPGCBL), which is constructing Matarbari power plant in Cox’s Bazar.
31 March 2024, 18:00 PM